Requirements for loading: to shorten the time, to ensure the yield of the alloy elements, to reduce the power consumption and to increase the lining of the furnace
Before loading, the batching workers should be carefully proportioning according to the requirements of the planned furnace number and steel type. According to the requirements of different steel technology, the burden should be carefully analyzed and calculated and the ingredients are accurately proportioning. Therefore, it is necessary to confirm the composition and alloy composition of the iron and steel material needed before loading, and check the measuring instruments, so as to ensure the proper chemical composition and accurate weight after melting, so as to facilitate the smooth operation of smelting.Super High Temperature Induction Vacuum Heat Treatment Graphitization Furnace
In order to achieve the density, it is necessary to rely on the reasonable collocation of large, medium and small furnace materials. The furnace material is dense, can be obtained once, and can improve the conduction and heat transfer performance of the furnace material. When the electrode is well, the arc is stable and is beneficial to melting. Usually, the charge is less than 10kg is called small material, 10~25kg material is more than 50kg, called aniseed. When loading, the furnace material of different capacity electric furnace has different size requirements, but the maximum of the furnace material must not exceed the 1/50 of the total burden of the furnace.
Silver Customized Tungsten Crucible For Vacuum Furnace
The cloth is more important, generally is part of small material miscellaneous iron installed in the basket bottom, above the small material, the center part of the charging basket loaded aniseed or refractory material, intermediate small fill material, so smooth and non porous, so that is conducive to conductive, and electrode broken bridge and eliminate material to prevent the collapse of material. The rest of the small and medium-sized material installed in refractory material or aniseed on and around. At the end of the material, the heavy load of 0.02%~0.03% was loaded on the upper part of the basket to help the arc, stabilize the current and reduce the radiation damage to the cover of the furnace.pvd coating machine for hardware



Quick Reply Show Quick Reply
Users browsing this topic
Guest (2)
New Topic Post Reply
Forum Jump  
You can post new topics in this forum.
You can reply to topics in this forum.
You can delete your posts in this forum.
You can edit your posts in this forum.
You cannot create polls in this forum.
You can vote in polls in this forum.

Powered by YAF 1.9.6 RC1 | YAF © 2003-2018, Yet Another Forum.NET
This page was generated in 0.093 seconds.

Copyright © 2012 Loftygolf.com